The following road segments will undergo pulverization and resurfacing. As part of this work, the Township will place a minimum of 0.15 m of granular material across the entire surface area prior to final surfacing. The surface treatment selected for all 2026 road projects is double surface treatment, which consists of applying an asphalt emulsion to the granular surface. This emulsion acts as a binding agent, stabilizing the aggregate to create a uniform, pavement-like surface in a cost-effective manner.
- Concession 4, Plantagenet (1.3 km)
- Concession 5, Plantagenet (2.1km)
- Concession 4, Alfred (2.2 km)
- Concession 5, Alfred (2.2 km)
- Lac Georges Road (1.7 km)
Budget : $1,042,000
Construction start date : May 2026
Tender : Closed