The following road segments will undergo pulverization and resurfacing. As part of this work, the Township will place a minimum of 0.15 m of granular material across the entire surface area prior to final surfacing. The surface treatment selected for all 2026 road projects is double surface treatment, which consists of applying an asphalt emulsion to the granular surface. This emulsion acts as a binding agent, stabilizing the aggregate to create a uniform, pavement-like surface in a cost-effective manner.
- Concession 4, Plantagenet (1.3 km) Resurfacing on May 6 to 7 2026.
- Concession 5, Plantagenet (2.1km) Pulverizing on May 4 and resurfacing May 8 and May 11 2026.
- Concession 4, Alfred (2.2 km) Pulverizing on May 5, 2026 and resurfacing May 12 to 13 2026.
- Concession 5, Alfred (2.2 km) Pulverizing on May 6, 2026 and resurfacing May 14 and 15 2026.
- Lac Georges Road (1.7 km) Resurfacing on May 4 to 5 2026.
Budget : $1,042,000
Construction start date : May 2026
Tender : Closed